Casey's Aquatic and Recreation Centre delivered on time and budget


The grand public facilities within 'the ARC'

[From PSA Project Newsletter - July 2002]
PSA Project provided total project management services for this landmark and award winning project for the City of Casey. PSA Project worked with the City Council from initial conception, through feasibility, design, procurement and final delivery of the centre.

The City of Casey's newest facility, the Aquatic and Recreation Centre, the [Casey]-'ARC' as it is affectionately known, is proof (if it is needed) that with proper management goals can be achieved. The project was achieved within budget, to the agreed programme and has met all the stakeholders requirements in terms of quality and operations.

For more information about this project, see the Casey Aquatic Centre listing in our project portfolio.

To view the rest of this newsletter Send us an email.

This project was successfully delivered using a "positive novation" contract and very detailed project planning and monitoring. It was also developed using a co-operative project and risk management methodology and we worked closely with our stakeholders to eveolve the best outcome in what would become an award winning project.

An insight into the award winning aspects of the ARC

PSA Project worked closely with the City of Casey to initially confirm the feasibility for the project and to establish key objectives for the development in terms of time, cost and quality, whilst at the same time managing the significant risks that such a project presents.

Once confirmed as a feasible project, PSA Project ensured the design team selection was undertaken to achieve the agreed goals and to meet the probity requirements of a Council tender.

Similarly the project Construction tender process was detailed and focused on achieving the best outcome for the project. Fletcher Construction won the tender, which was for a Novated Design and Construct responsibility. Fletchers were contractually responsible to Council for the final detailed design and delivery of the project in accordance with the detailed design brief previously developed and signed off for the project. A similar approach is being used in the delivery of the MCG Northern Stand redevelopment with Grocon and has been used by PSA Project to deliver many successful projects. For further information on the Novation process and how this can be of benefit to you please read more about it or contact us.

To view the rest of this newsletter Send us an email.

The entrance even eludes to a wave of enjoyment found within

PSA Project detailed planning and contract control ensured the delivery and commissioning of the project was achieved to all stakeholders satisfaction. The centre has been well received by the community and occupancy rates are above expectations.

A well planned, managed and developed project that has created a landmark facility for the growing Casey Community.

The centre was delivered under budget, to programme and the agreed quality.

For further details on the Casey-ARC see the PSA Project online portfolio. Contact us if you want further details of how we can provide the benefits of the Casey ARC experience to your projects.

Related Information:

View the rest of this newsletter

View PSA Project's Portfolio

View the PSA Project homepage

Close Window


A grand sight to behold
 
To view the rest of this newsletter Send us an email.
Home | Project Management | Project Management Services | Project Management Software
Contact Us | Site Help
| Site Map | Privacy Policy | Terms of Use

Copyright © PSA Project Management 2005, All Rights Reserved
Optimised for IE5.5 & 800x600 screen resolution
Send Web Site Feedback to webmaster